Project AETHER

A super-pressure balloon probe to the habitable cloud layer of Venus.

NEPHELIS.MCC · PHASE DESIGN · LAUNCH TARGET 2027-12-15

Why the Cloud Layer?

Between 50 and 60 kilometers above the surface of Venus lies a region with Earth-like temperatures (0–60°C) and pressure (~1 atm). This is the only place in the inner solar system, besides Earth itself, where humans could potentially live without extreme life support.

Mission Concept

AETHER will deploy a long-duration super-pressure balloon carrying a suite of instruments for atmospheric sampling, imaging, and in-situ analysis. The probe will float for weeks or months, providing unprecedented data on this unique environment.

Probe specs

  • Type: Super-pressure balloon
  • Altitude: 5060 km
  • Temperature: 060 °C
  • Instruments: Atmospheric spectrometers, High-res cameras, Meteorological suite, Life detection experiments
  • Wet mass class: ~400 kg · balloon ~6.6 m

Mass budget (summary)

ElementMass (kg)
Kick / transfer stage (wet)330380
Entry probe + balloon + gondola (dry stack)150200
Heatshield / blunt-body base5060
Fluoropolymer balloon + inflation3545
Gondola + sensor suite4055
Avionics, power, structure, comms2535

Positive headroom vs 400 kg wet — acid protection, helium, redundancy

Mission control checklist

  • in_progressMission requirements baseline signed (v0.9 draft in docs/)2026-Q3
  • in_progressCONOPS v1 (v0.9 draft in docs/conops-v0.9.md)2026-Q3
  • plannedPDR-lite: balloon + gondola ICD freeze2026-Q4
  • plannedAcid / materials coupon campaign complete enough for fab decision2026-Q4
  • plannedSensor suite baselined with mass/power/data numbers2026-Q4
  • plannedComms architecture review (CubeSat relay / hybrid)2026-Q4
  • plannedCDR-lite: drawings, BOMs, test plans2027-Q1
  • planned50% of $500k goal committed2027-Q1
  • plannedEnvironmental qualification campaign executed2027-Q2
  • plannedSystem integration & inflation sequence tests pass2027-Q2
  • plannedLaunch path LOI or rideshare reservation2027-Q2
  • plannedFlight software freeze + ops playbook v12027-Q3
  • plannedMission ops rehearsal complete2027-Q3
  • plannedFlight stack accepted and shipped to launch site2027-Q3
  • plannedLaunch + successful Venus transfer injection2027-Q4
  • plannedSuccessful inflate + ≥30 days float with science downlink2028-Q1

Top open risks

RISK MATRIX · OPEN / MITIGATING
likelihood →impact →01020304050607
  • R-01 Acid degradation of balloon envelope
  • R-02 Entry / inflation sequence failure
  • R-03 Comms blackout / insufficient downlink
  • R-04 Launch rideshare slip past 2027 window
  • R-05 Crowdfund / partner capital shortfall
  • R-06 Planetary protection / DNA tier regulatory delay
  • R-07 Sensor mass growth eats float margin
  • R-01 Acid degradation of balloon envelope (high/medium) — Multi-layer fluoropolymer; altitude selection; coupon protocol in docs/materials-coupon-test-protocol.md
  • R-02 Entry / inflation sequence failure (critical/medium) — Redundant inflation path; extensive drop / vacuum tests; VEGA lessons
  • R-03 Comms blackout / insufficient downlink (high/medium) — 3U CubeSat relay architecture; store-and-forward; power budget margin
  • R-04 Launch rideshare slip past 2027 window (high/medium) — Multiple vehicle options; mass keeps rideshare-compatible; early LOI talks
  • R-05 Crowdfund / partner capital shortfall (high/medium) — Stripe tiers live; sponsor outreach; in-kind hardware path

Full register in data · public roadmap at /roadmap.

Data-driven from mass-budget.json, mission-control.json, risks.json, specs.json, power-budget.json.